Construction ongoing - data updated September 2026

Construction Progress and Project Updates

Current Surat Metro status: the Rs 12,020.32 crore project covers 40.35 km across two corridors with 38 stations. The first trial run took place on 29 March 2026 on the 8.5 km Diamond Corridor between Dream City and Althan Tenement. This page tracks every major Surat Metro update from foundation stone to commercial launch.

Overall Project Progress

Total network

40.35 km

2 corridors, 38 stations

Project cost

Rs 12,020 Cr

~US$1.2 billion

Trial run

8.5 km

Diamond Corridor live

Underground tunneling

6.47 km

All 3 TBM breakthroughs done

Construction milestones completed

Civil works (elevated viaducts, stations)Trial run active
Underground tunneling (6.47 km, 3 TBMs)Complete
Rolling stock (Titagarh Rail Systems)Delivery in progress
Signaling and systems (DB Engineering)In progress

Corridor-Wise Breakdown

Corridor 1 - Red Line

Sarthana to Dream City, running north-south through the city centre. Includes Surat's only underground metro section - a 6.47 km stretch from Kapodra to Gandhi Baug built by 3 TBMs.

Total length
21.61 km
Stations
20
Elevated
15.14 km / 14 stations
Underground
6.47 km / 6 stations
Depot
Dream City
Trial section
8.5 km active
Red Line details

Corridor 2 - Green Line

Bhesan to Saroli, running east-west across the city. Entirely elevated with no underground sections. Dilip Buildcon holds the two largest civil packages (CS-5 and CS-6) covering a combined 19.261 km of viaduct.

Total length
18.74 km
Stations
18
Elevated
18.74 km / 18 stations
Underground
None
Depot
Bhesan
Trial status
Trial underway
Green Line details

Trial Run Status

Diamond Corridor - First Trial Run

The first trial run launched on 29 March 2026 on the 8.5 km elevated section from Dream City to Althan Tenement on the Red Line. This stretch is called the "Diamond Corridor" because it connects directly to the Surat Diamond Bourse, the world's largest diamond trading hub. Seven stations were completed at the time of the trial.

Date
29 March 2026
Section
Dream City to Althan Tenement
Distance
8.5 km
Testing scope
500+ hours planned

Testing covers safety mechanisms, braking, speed performance, and security protocols. RDSO and CMRS independent inspections are required before the section opens for commercial passengers. The east-west corridor (Green Line) has also begun trial runs.

Underground Tunneling Progress

All 6.47 km of underground tunneling on Corridor 1 is complete. Three tunnel boring machines (TBMs) excavated twin tunnels between Kapodra and Gandhi Baug, passing through 6 underground stations in the old city centre.

TBM Amrit

Achieved breakthrough at Chowk Bazar Station in August 2025. Named after the "Amrit Mahotsav" celebration of India's 75th independence anniversary.

Breakthrough complete

TBM Narmada

Named after Gujarat's Narmada River. Excavated through the dense urban core beneath Surat's historic textile market district, one of the most challenging stretches.

Breakthrough complete

TBM Tapi

Named after the Tapi River that flows through Surat. Completed the final underground tunnel segment, enabling full connectivity through the 6 underground stations from Labheshwar Chowk to Chowk Bazar.

Breakthrough complete

Underground stations (6)

Labheshwar Chowk
Central Warehouse
Surat Railway Station
Maskati Hospital
Gandhi Baug
Chowk Bazar

Stretch: Kapodra to Gandhi Baug, 6.47 km. All underground stations are on Corridor 1 (Red Line) only.

Project Timeline

August 2012

SMC proposed four rail routes for Surat

January 2017

Government of Gujarat approved two corridors

9 March 2019

Public Investment Board approved DMRC-prepared DPR

11 March 2019

Union government sanctioned the project

18 January 2021

PM Modi laid foundation stone, civil construction began

28 January 2021

AFD loan (EUR 250 million) signed for Phase 1

17 December 2021

KfW loan (EUR 442.26 million) signed

June 2023

Titagarh Rail Systems awarded Rs 857 crore rolling stock order

August 2025

TBM Amrit breakthrough at Chowk Bazar Station

October 2025

DB Engineering signed signaling and systems contract

29 March 2026

First trial run on 8.5 km Diamond Corridor (Dream City to Althan Tenement)

Mid-2026

Expected opening of first 8.5 km section

Dec 2026 / 2027

Full Phase 1 expected operational (both corridors)

Project Contractors

Five major contractors handle the civil works, rolling stock, signaling, and project consultancy. Dilip Buildcon holds the largest share of elevated viaduct construction across both phases of Corridor 2.

ContractorPackageValue
Dilip Buildcon (DBL)CS-6 (Phase 1)Rs 702.02 crore
DBL-RBL JVCS-5 (Phase 2)Rs 1,061 crore
Titagarh Rail SystemsRolling StockRs 857 crore
DB Engineering & ConsultingSignaling / SystemsNot disclosed
DMRC (Delhi Metro)ConsultancyConsultancy fee

Project Funding

The project is funded through a mix of government equity and international bilateral loans. The central and Gujarat state governments split equity contributions 50:50, with the French AFD and German KfW providing the bulk of debt financing.

Government equity

Equity (GoI + GoG, 50:50)

Proportional share

Source: Wikipedia

Bilateral loan

French Development Agency (AFD)

EUR 250 million

Source: The Metro Rail Guy

Bilateral loan

Germany Development Bank (KfW)

EUR 442.26 million

Source: Economic Times

Multilateral

Additional bilateral / multilateral loans

Remaining balance

Source: Wikipedia

Construction and Project Questions

When did Surat Metro construction start?

PM Modi laid the foundation stone on 18 January 2021, and civil construction began immediately after. The project was sanctioned by the Union government on 11 March 2019 following DPR approval by the Public Investment Board two days earlier.

How much does the Surat Metro project cost?

The total sanctioned cost is Rs 12,020.32 crore (approximately US$1.2 billion). Funding comes from central and state government equity (50:50 split), an AFD loan of EUR 250 million, and a KfW loan of EUR 442.26 million, with the remainder from additional multilateral sources.

Which section of Surat Metro had the first trial run?

The first trial run started on 29 March 2026 on the 8.5 km "Diamond Corridor" section between Dream City and Althan Tenement on the Red Line. This elevated section connects to the Surat Diamond Bourse and had 7 stations completed at the time of the trial.

How many tunnel boring machines were used for the underground section?

Three TBMs were deployed for the 6.47 km underground stretch on Corridor 1: Amrit, Narmada, and Tapi. TBM Amrit achieved its breakthrough at Chowk Bazar Station in August 2025, marking a major tunneling milestone for the project.

Who is building the Surat Metro coaches?

Titagarh Rail Systems won the Rs 857 crore order in June 2023 to manufacture metro coaches for both corridors. The trains run on standard gauge (1,435 mm) track with 750V DC third rail electrification and have a design speed of 80 km/h.

What is the current status of Surat Metro construction?

Trial runs began on 29 March 2026 on the 8.5 km Dream City to Althan Tenement section. Underground tunneling across all three TBMs is complete. The first commercial section is expected to open by mid-2026 after RDSO and CMRS inspections.